Revetment Project
On March 9, 2018, Governor Deal signed House Bill 683 which designated $10 million to the OneGeorgia Authority (the funding mechanism for the Georgia Department of Community Affairs) for beach renourishment projects. As such, the OneGeorgia Authority is seeking to issue a one-time grant in an amount up to $2.5 million in periodic reimbursement payments to Glynn County. Funds allocated to the County may be used for necessary studies, planning/consulting/engineering activities, obtaining necessary state and/or federal permits, construction or reconstruction of beaches and/or dunes (including dredging and placement of sand), location-appropriate natural vegetation necessary to maintain dunes, construction/reconstruction of dunes, installation of rock revetments, or other activities deemed appropriate by the OneGeorgia Authority. Per the terms of the extended agreement, work is to be completed by April 30, 2021, or the County will forfeit the balance of funds.
U.S Army Corps of Engineers Permit
Georgia Department of Natural Resources Letter of Permission
- Project Permit Letter and Grant Extension
- Project Timeline
- 2019 Project Phase Maps
- 1965 Original Project Maps
- BOC Presentations
- FAQ
- March 9, 2018 - Governor Deal signed House Bill 683 which designated $10 million to the OneGeorgia Authority for beach renourishment projects.
- September 6, 2018 - Board of Commissioners approvesMOA with OneGeorgia Authority
- December 6, 2018 - Board of Commissioners approves theProposal for consulting from Applied Technology and Management
- February 19, 2019 - Board of Commissioners receivespresentation in work session from ATM
- March 19, 2019 - Board of Commissioners receives anupdated presentation in work session from ATM
- April 1, 2019 - Project Permit Letter Sent to Army Corps of Engineers and Georgia Department of Natural Resources for approval
- February 17, 2020 -Permit Extensiongranted. The revised award period end date is April 30, 2021
- June 9, 2020 - Received approval from Army Corps of Engineers and Georgia Department of Natural Resources
- Current - November 2020 through April 2021 - Proposed Phase 1 Construction
- April 30, 2021 - Money received from OneGeorgia Grant must be used or returned to the state. @(Model.BulletStyle == CivicPlus.Entities.Modules.Layout.Enums.BulletStyle.Decimal ? "ol" : "ul")>
7/17/19 There are already rocks on my property. Why additional rocks to be added?
The intent of the maintenance project is to raise the level of the entire revetment structure to approximately 8.5ft to adequately protect the upland area. By granting permission to permit the maintenance activity on your property (checking yes) you will not incur any cost. Nor does it guarantee that any work will be done. We have received $2.5M from the state for this work, but that will not be enough to complete the entire project. During this first construction phase (November 2019 to April 2019) construction will focus on the areas of the revetment that front public property. Funding for future phases of the project is uncertain, but having a permit in place will speed up the process should we have additional resources available to fund the project. The permit will be in place for 5 years.
7/17/19 If I approve my property to be included in the project, is there any cost to me?Once the permit to conduct the work on the revetment is obtained, we are planning to provide an opportunity for private land owners to “piggy back” on the permit. In this scenario, a private land owner would provide the financial resources to complete the maintenance project on their property using the County’s contractor who is hired to do the first phase of the project. There is no requirement that you opt in to this opportunity, only that the opportunity is available to you should you decide to take advantage of it. Once we bid the project out and have a contractor for the first phase of the work, we will be able to provide additional instructions as to how property owners can piggy back on our contractor. In the meantime, we will attempt to seek state money to complete the project in a later phase, however, there is no guarantee that will be granted.
5/15/19 If Glynn County has a 5-year permit in place for the entire area, will homeowners be able to hire their own contractors to do the work?
The applicant for the revetment rehabilitation regulatory permits is Glynn County. This means that only the applicant may authorize construction under the permit. Each phase of construction will be authorized and under the control of Glynn County which means the County must hire the contractor and manage project construction. No private homeowner would be authorized to hire a contractor and rehabilitate the revetment privately under the County permits. The US Army Corps of Engineers USACE is of the understanding that the project will be completed in phases, by the applicant, as shown in the permit plans.
According to the (USACE), the only property owners required to provide permission to the County to obtain the requested permit for the revetment rehabilitation project are the property owners with revetment directly on their property as seen on the Glynn County GIS parcel layer. It appears that property owners whose property line does not encompass the revetment structure will not be required to give permission because the revetment is on County/public property.
5/15/19 What height will the revetment rocks be at the highest? Is there enough money in the grant to cover the entire permitted area?
The purpose of the project is to improve coastal storm protection and resilience. The intent is to conduct maintenance on the existing structure with similar materials and construction methods to rehabilitate the revetment back to a condition that provides protection to the upland and upland infrastructure from wave attack during storms and high tide events. To accomplish this, the proposed design crest elevation for the revetment rehabilitation will be raised to +8.5’ NAVD88, or about one foot above the original 1960s design elevation (+7.5’ NAVD88). The rehabilitated structure footprint would remain within the footprint of the existing structure, or the work would not be considered maintenance. Raising the crest elevation is necessary to increase the resiliency of the structure, account for sea level rise since original construction, and provide additional coastal storm protection.
The County has identified that the initial phase of construction (2019‐2020 construction window with the OneGeogia Grant funds) may necessarily be limited to the revetment maintenance fronting public parcels only. Initial cost estimates were based on recent comparable type construction costs for Jekyll Island. However, ATM has identified to the County that revetment rehabilitation construction costs are volatile, due to availability and location of materials suppliers, contractor availability, project location and access (particularly so for St. Simons Island due to limited access and the need to work around tides), and fuel costs, among other factors. In addition, any regulatory restrictions or conditions can affect project costs. For these reasons, the final project length that can be completed as the first phase under the available funds to the County will not be fully known until the project is bid.
5/15/19 How will homeowners be notified?
The County plans to send out two different letters. One to notice all property owners fronting the revetment of the upcoming revetment rehabilitation project. Second, Per USACE requirements, the County is seeking permission to permit placement of rocks along revetment on private property. Any property owner who does not want to participate in the project should notify the County after receiving the notice.
5/15/19 What properties have priority placement?
The County has determined that the first phase of revetment rehabilitation will occur to the +8.5 ft NAVD elevation at parcels fronting public properties during the 2019-2020 construction window. Future phases, pending available future funds, will involve rehabilitating the revetment in front of private residences in order of most vulnerable as determined by the County. Vulnerability will be evaluated by a variety of criteria such as elevation of existing revetment crest, residence proximity to revetment, beach berm elevation in front of revetment, size of stone in revetment section, and by site evaluation.
5/15/19 How will older/historic properties be addressed in the scope of work?
The USACE has asked Glynn County to locate any structure older than 50 years within 100 meters of the Highest Astronomical Tide (HAT) line (+5.0’ NAVD88). These properties will be reviewed by the USACE for a Section 106 evaluation, which is part of the review and processing of the USACE permit. The goal of a Section 106 evaluation is to determine if the revetment rehabilitation will alter the integrity of the historic structure in any way. Appropriate offsets and boundaries will be set, if necessary, after evaluation of each property. The 100 meter 106 buffer does not necessarily imply a “no work zone.” Section 106 is just one of the many aspects of potential impacts that the regulatory agencies consider during their permit processing.
Projected timeline (Excludes weekends and holidays): | Dates: |
---|---|
Wyley Street | October 19-21, 2020 |
Frazier street | October 21-23, 2020 |
Hamilton Street | October 26-27, 2020 |
Virginia Street | October 27-29, 2020 |
Florence Street | October 29- November 2, 2020 |
Georgia Street | November 2-3, 2020 |
Wyley street Crossover | November 2-6, 2020 |
Floyd Street | November 3-4, 2020 |
Postell Street | November 4-6, 2020 |
Neptune park, Mallery, and 12th Street | November 9-December 1, 2020 |
Postell Street Crossover | November 9-13, 2020 |
Neptune Park Crossover | December 1-7, 2020 |
Beachview Drive | December 2, 2020 |
10th Street | December 3-4, 2020 |
9th Street | December 7-8, 2020 |
8th Street | December 8-10, 2020 |
9th Street Crossover | December 9-16, 2020 |
7th Street | December 11, 2020 |
6th Street | December 14, 2020 |
5th Street | December 15-16, 2020 |
4th Street | December 17, 2020 |
3rd Street | December 18, 2020 |
2nd Street | December 21, 2020 |
1st Street | December 22, 2020-January 1, 2021 |
Myrtle Street | January 4-6, 2021 |
Cedar Street | January 8-11, 2021 |
Myrtle Street Crossover | January 8-14, 2021 |
Neptune Road | January 12, 2021 |
Goulds Inlet | January 13-22, 2021 |